When is a FAI required?

Last reviewed: 17 October 2026

The question is rarely whether a FAI is needed. It is almost always whether the whole thing has to be done again, or only part of it. That distinction decides whether the work is an afternoon or a week.

The principle behind the triggers

A FAI is evidence that a specific manufacturing process can produce a conforming part. So the question that decides whether a new FAI is needed is not “did the drawing change” but “does the existing FAI still describe the process actually being used”.

If it does not, the old FAI no longer proves anything about the current process.

Full FAI: commonly published trigger events

TriggerWhy it invalidates the baseline
New part number, or first build to a customer designThere is no baseline at all.
Design change affecting fit, form, function, safety or performanceThe requirements the old FAI verified have changed.
Production lapse — commonly 24 months or moreThe process has not been demonstrated to be under control since it last ran. Customers may specify a shorter or longer interval.
New manufacturing siteDifferent facility, different process realisation.
New primary equipment or new process routeThe capability being relied on is not the capability that was validated.
Change of material, source, or a key special processHeat treat, plating, bonding and welding changes can affect a part in ways a dimensional re-check will not capture.
Customer-directed FAIA purchase order, quality clause or corrective action can require it regardless of the above.

Widely published as triggers for a full FAI. Your customer’s flowdown can be stricter than this list.

Partial (delta) FAI: when less is enough

A partial FAI covers only the characteristics affected by the change, and references the original baseline report by number and date. It is typically acceptable where the change is tightly scoped and the unchanged process is still demonstrably in control.

ChangeCommonly treated as
Drawing typo or spelling correction, no requirement changePartial FAI
Clarified inspection method, same requirementPartial FAI
Removal of an unused reference dimensionPartial FAI
Cosmetic or deburr note clarification with no critical impactPartial FAI, with customer agreement where required
New machining centre and fixture for the same partUsually full FAI — the manufacturing environment changed

Illustrative only. The decision is yours, or your customer’s, based on the actual risk and the applicable flowdown.

Boundary cases are where the arguments happen

Two changes that look similar on paper can land differently:

A widely used tie-breaker: if the risk is unclear, default to the fuller FAI. It is cheaper than a rejected submission or a late containment.

What this means for the paperwork

For the people assembling the package that is the practical consequence: much less Form 3 data, but it still has to be structured, and the reference back to the baseline still has to be correct. Getting Form 3 data into Excel.

This is orientation, not the standard. AS9102 is published by SAE International and is revised from time to time. Field names, requirements and trigger conditions can change between revisions, and your customer’s flowdown can be stricter than the standard. Always work from the current published edition of AS9102, and from your own contract and quality system. Nothing on this page is compliance advice.
Retyping these columns by hand? The converter reads an AS9102 Form 3 and fills all 15 columns for you, in your browser, with nothing uploaded. Three pages free, no account.

Frequently asked questions

How long a production gap requires a full FAI?

A common aerospace rule is 24 months or more, unless the customer specifies a different interval. The underlying question is whether the existing FAI still describes the process actually in use, so a customer can specify shorter or longer.

Can a drawing typo correction be handled with a partial FAI?

Edits that change no requirement, such as spelling, unit symbols, unused reference dimensions or clarified inspection methods, are commonly handled as a partial or delta FAI. Where a change touches fit, form, function, safety or performance, a full FAI is the usual expectation.

Does moving production to a new machine require a full FAI?

Typically yes when the change affects the capability being relied on, such as a new machining centre, a new fixture locating a critical feature, or a move from manual to automated production. The drawing may be unchanged while the validated process is not.

What is a delta FAI?

Another name for a partial FAI: a submission covering only the characteristics affected by a change, referencing the original baseline report by number and date rather than restating the full inspection.

Sources

Standards are revised. Always work from the current published edition of AS9102 from SAE International. This page is orientation only and is not a substitute for the standard.